|
1
|
- First patented in 1893
- Primary use was in dimensional stone production, with black powder
- Currently used extensively in wall control
- Applications in production holes
|
|
2
|
- Top air deck – improve fragmentation in surface (stemming) zone of blast
- Mid-column air deck – replace inert decks with improved fragmentation in
the central (inert deck) zone of the blast
- Bottom air decks – reduced for sub-drilling
- Generally improve energy distribution
|
|
3
|
- Replace expensive and time consuming use of lineal decoupled charges
- Expand spacings and/or reduce loads used with open hole, bottom charge designs
- Reduce air-blast complaints
- Extend time of pressure pulse on wall
|
|
4
|
|
|
5
|
- Computer modelling
- High speed photography
- Precise electronic detonators
- Recognition of benefits
- Controlled test environment
- Cost reduction incentives
|
|
6
|
- Standard load, fully stemmed hole
- Top air deck of 1.44 meters
- mid-column air deck
- bottom hole air deck
- pre-shear with inert decks
- pre-shear with lineal decoupled charge
- pre-shear with air deck
|
|
7
|
|
|
8
|
|
|
9
|
|
|
10
|
|
|
11
|
|
|
12
|
|
|
13
|
|
|
14
|
- Stemming depth = 50% to 75% original stemming depth
- Length of air deck = 20% to 40% x (air + explosives) +/-
- Maximum explosives to remove = 20% of original explosives load
- Minimum explosives to remove = cost of air deck device
|
|
15
|
- Stemming depth = adjust to maintain SDOB constant
- Length of air deck = 20% to 40% x (air + explosives) +/-
- Maximum explosives to remove = 20% of original explosives load
- Minimum explosives to remove = cost of air deck device
- Precise timing to initiate both charges simultaneously
|
|
16
|
|
|
17
|
|
|
18
|
- Stemming depth = adjust to maintain SDOB constant
- Length of air deck = 20% of (air + explosives) +/-
- Maximum explosives to remove = 20% of original explosives load
- Minimum explosives to remove = calculate based on savings due to reduced
drilling cost plus cost of air deck device
- Precise drilling control to maintain center of all air decks at the
desired floor elevation
|
|
19
|
|
|
20
|
|
|
21
|
|
|
22
|
|
|
23
|
- Stemming = 9 to 12 x borehole diameter
- Spacing = 12 to 15 x borehole diameter
- Burden = 15 to 18 x borehole diameter
- Charge = 0.5 to 1.0 kg/square meter of wall per hole
- Deep holes, support 1/3 of total
charge at mid-point
- Very deep holes, support 1/3 of
total charge at 2/3 depth, 1/6 of
total charge at 1/3 depth
|
|
24
|
|
|
25
|
- Wide variety of materials
- iron ore, soft to very
hard, production
- limestone quarry, production
- copper, production, wall control
- poly-metallic, wall control
- coal, production
- gold, production and wall
control
|
|
26
|
- Using air decks prepared with jute bags manually filled with drill
cuttings, lowered and secured
with rope
- Three man crew, 3 minutes per
hole to prepare
- 1.5 meter air deck
- 7.0 meters stemming on top of bag
|
|
27
|
- Air bags, inflated with brake
system of bulk loading truck
- One man (ground technician with truck) placing air bags – 15 seconds per
hole
- Approximately 50% reduction in loading cycle time
- Recommended reducing stemming to 6.0 meters, maintain same explosives charge
|
|
28
|
- Three decks with inert stemming
- Three man crew, 5 minutes per
hole to complete
- 3.0 meters top stemming
- Individual Nonel and primer in each deck
|
|
29
|
- 3.0 meters top stemming
- Top air deck of 3.3 meters
- Single bottom charge, sum of
three decks normally used
- Single Nonel and primer
- One man (ground technician with truck) placing air bags – 15 seconds per
hole
|
|
30
|
- Approximately 33% reduction in loading cycle time
- Same fragmentation results as with standard design
- Recommend testing with 4.0 meter mid-column air deck, top stemming of 2.75 meters
|
|
31
|
|
|
32
|
|
|
33
|
- Using 1.5 meter bottom hole air decks as standard
- Mechanical plug, rope supported
- Between 90 and 120 seconds per hole to measure hole, prepare and place plug
- Two crew operation, plugs placed
in advance of loading operations
|
|
34
|
- Air bags, inflated with brake
system of bulk loading truck
- One man (ground technician with truck) measure holes and place air bags
– 15 to 20 seconds per hole
- Maintained same air deck configuration
- Same fragmentation results and floor conditions as with standard design
|
|
35
|
- Production Holes
- 8.0 meters top stemming
- Wall control
- 65 kg bottom load
- 2 to 4 meters stemming immediately on top of bottom load
|
|
36
|
- Production
- Removed 1.0 meter of explosives
- Stemming at 6.0 meters, 3.0 meter
air deck
- Stemming at 5.3 meters, 3.7 meter
air deck
- Wall control
- Maintain same bottom load
- Air bag at 3.0 meter, fully
stemmed above
|
|
37
|
- Production
- At 6.0 meters stemming, improved
swell
- At 5.3 meters stemming, improved
swell, surface fragmentation
- Wall control
- Reduced back-break
- No cratering
|
|
38
|
|
|
39
|
|
|
40
|
|
|
41
|
|
|
42
|
|
|
43
|
|
|
44
|
|
|
45
|
|
|
46
|
|
|
47
|
|
|
48
|
|
|
49
|
|
|
50
|
|
|
51
|
|
|
52
|
- Standard load
- 150 kg bottom charge, open hole
- approximately 1.3 kg/sq meter of wall
- Tests, maintained same charge
- 1/3 of charge supported on air bag at mid-depth of hole
- Air bag at 3.0 meters from top of hole,
fully stemmed above air bag
|
|
53
|
- Standard load
- surface craters of from 2.0 to 2.5 meters radius
- Supported charge
- surface craters of approximately 1.0 meter radius
- Air bag at 3.0 meters
- surface craters of from 2.5 to 3.0 meters radius
|
|
54
|
- Reduce charge to 1.0 kg/sq meter of wall
- Test with combination of supported charge and top stemming :
- 75 kg bottom load
- 37.5 kg supported at mid-point
- air bag at 2.0 meters, fully
stemmed above air bag
|